Teen Center for Boys & Girls Club

Teen Center

The City of Leesburg in partnership with The Boys and Girls club is constructing a 11,637 square feet addition to the existing recreation center. Currently the project is 25% complete with a tentative completion date of November 22, 2021. Major items completed includes site grading, fill and compaction for the foundation, installation of underground electric and plumbing conduit, installation of the foundation, construction of the block walls and structural steel supports. Upcoming work includes the installation of the roofing system; mechanical, electrical and plumbing rough-in; interior framing; and installation of the storefront. 

CONTRACTOR: Evergreen Construction
Cost: $2.7 Million
Start Date: 05/17/2021
Completion Date: Winter 2021

Construction Phase